Dedicated road marking team mobilised throughout the Highlands
Highland Council’s dedicated road marking team has been fully mobilised to carry out road marking across the Highland region.
Chair of Highland Council’s Economy and Infrastructure Committee, Councillor Ken Gowans, said: “The Council has invested significantly in road maintenance as part of a broader program to improve Highland roads and the dedicated road marking team will help us to improve road safety for our communities. I’m delighted to see that the newly established team has made the most of the recent good weather to cover a lot of ground in the north-west and Skye, despite the challenging geography. Our new vehicles are also ensuring that the work is carried out quickly and effectively with minimal disruption for local people.”
Since April, the team has completed approx. 150km of white lines across Sutherland, Caithness and the Isle of Skye, with a further 190km of white lining works planned for over the summer months across the other areas of the Highlands, including Lochaber, Ross and Cromarty, Badenoch and Strathspey and Inverness. Exact timings will be weather-dependent, but we aim to give communities advance notice on social media wherever possible.
The operation requires a team of four operatives using two lorries. A feeder lorry is used to preheat and deliver the thermoplastic lining material to the lining lorry which then applies the hot material to the road surface as either an edge or centre line. Immediately after the line is applied, another nozzle adds reflective glass beads, followed by a final nozzle spraying clean water onto the line to cool the material, allowing traffic to flow immediately.
The road marking programme forms part of The Council’s £2.1 billion Highland Investment Plan which will provide 20 years of funding for roads and transport, schools, offices and community facilities throughout the Highlands.

A836 gills bay

B8084 broadford to elgol