Pending works schedule April 2025 S18
|
Works number |
Watercourse name |
Location |
Date for re-inspection* |
Description of works |
|---|---|---|---|---|
|
580 |
South Kessock Seawall |
3 Areas in the seawall |
20/01/2026 |
Repair missing stones sets in the seawall |
|
626 |
Mill Burn |
Culvert under Sir Walter Scott Drive |
08/09/2025 |
Remove all silt and stone deposation from the inlet and ditch 10m upstream from the inlet |
|
633 |
Druid Temple Burn |
Next to the playing ground at Grebe Avenue Hall |
08/09/2025 |
Remove all vegetation lying in and across the burn which is restricting forward flow of water |
|
635 |
Ault na Skiah |
Adjacent to the Distributor Road (B8082) behind properties on Castle Heather Avenue |
10/06/2025 |
remove silt accumulations from the culvert inlet which has reduced the culvert width by approx 50%, please remove any self seeded trees that are growing in the burn or on the burn sides. |
|
636 |
SWFRC |
SWRFC numerous locations |
03/09/2025 |
Remove all vegetation gorse/whin are growing on the crown and sides of the flood relief channel. Currently growing is numerous areas |
|
658 |
Slackbuie Channel |
Junction of Culduthel Road and Green Drive |
10/06/2025 |
Silt accumulations and a build up of debris/rubbish at the culvert,some of which is lying at the twin culvert inlets, please remove as much silt as possible and ensure inlets are clear. |
|
664 |
Ault na Skiah |
Culvert outlet opposite Evan Barron Rd |
08/09/2025 |
The culvert outlet is 50% surcharged due to windblown trees and woody debris lying across the watercourse for the majority of the open section down to the boundary fence of the property. Clear all woody debris from the open section. |
|
724 |
Knockbain Burn |
Knockbain Burn, near Gorstan, Dingwall |
01/05/2025 |
Build up of Silt on LHS near Screen - Should be cleared |
|
738 |
Holm Burn |
Underneath Bridge on B862, near Holm Lodge. Inverness |
08/09/2025 |
Tree Limb stuck underneath Bridge on B862. Limb will need to be removed. |
|
741 |
Park Burn |
Park Road,Sstrathpeffer |
06/05/2025 |
Partial blockage and likely collapse of stone culvert within 2m of Manhole. Section is estimated to be below footpath. Callapse to be repaired and blockage removed. |
|
743 |
Guisach Burn |
Treasures of the Earth Museum |
26/04/2025 |
Screen blinded by sediment. BEAR contacted to clear the screen. |
|
744 |
Mill Burn |
Section between Mason Road & Teal Avenue |
10/06/2025 |
Fallen Trees lying within the Watercourse accumulating Derbis. Trees & Debris to be removed to ensure un-restricted flow. |
|
748 |
Gergask Burn |
Culvert under single track road near Am Bothan, Laggan |
06/08/2025 |
Culvert Inlet blocked with Wooden debris & Large Tree Branch, should be removed to ensure un-restricted flow |
|
749 |
Eil Burn |
Screened Inlet to Culvert under Station Road (A862), Conon Bridge |
07/05/2025 |
Inlet area silted up which has raised the bed of the watercourse, silting the Screen Inlet by approx. 50%. Silt should be removed surrounding the Inlet. |
|
751 |
Culloden Burn West |
Outlet of Culvert, next to Gruffalo carving |
09/09/2025 |
Burn blocked with cluster of Woody debris, should be cleared to ensure un-restricted flow |
|
754 |
Olrig Cemetery Burn |
Within Farm field east of St Trothan's Church, Olrig Cemetery, Castletown |
18/08/2025 |
Multiple fallen trees & concrete slabs lying within Burn D/S from Outlet, this should be cleared to ensure un-restricted waterflow. Section 18 letter issued |
|
758 |
Culloden Burn West |
Ferntower Avenue |
15/08/2029 |
Jetting required to clear debris in culvert. |
|
766 |
Ault Na Skiah |
Upper Slackbuie, near Electricity Distribution Site, Inverness |
06/05/2025 |
Screen 50% blocked with washed down stones & debris. Screen to be cleared. |
|
769 |
Slackbuie Spring |
ASDA Superstore, Slackbuie, Inverness |
10/06/2025 |
Significant amount of litter/ rubbish surrouding the watercourses of Slackbuie Spring & Channel, overgrown with debris blocking Inlet of culvert. S18 Letter to have rubbish, veg & debris removed. |
|
770 |
Ault na Skiah |
Lodge Road, Inverness |
29/04/2025 |
Large pile of side-cast debris placed on RHS of Culvert Inlet area by Homeowner, should be removed to ensure unrestricted flow. Issue S18 Letter |
|
771 |
Smithton Burn |
Woodside Village, Westhill, Inverness |
11/06/2025 |
Rubbish & dumpings by Inlet area, S18 Letter issued to remove |
* The stated date for re-inspection denotes when the re-inspection is due and not when the works are due to be carried out