Project outline
Welcome to the project page for Dingwall Community Point of Delivery (PoD).
Here you can read about the plans and track progress.
Get in touch with the project team.
Investment
The Council is building a new Dingwall Primary School and St Clement's Special School in Dingwall, scheduled for completion in 2030.
As part of the Highland Investment Plan, all new school buildings will be designed as Community Points of Delivery (PODs), with the flexibility to accommodate education provision alongside other community facilities, council services and partner organisations, within modern, locally accessible community hubs.
The multi-million-pound investment will see both schools accommodated in one campus building. Within the building, each school will retain their individual identities, with their own name, staff, management, entrance, car-parking and facilities.
The Dingwall Community PoD will incorporate:
-
A new Dingwall Primary School, including Gaelic Medium Education and Early Years provision. The school will have capacity for 456 children and 88 early years places.
-
A new St Clement’s Special School, with capacity for 76 pupils.
-
Flexible office space for council and partner agency staff.
-
A disability sports centre.
-
A 3G synthetic pitch, offering community access out-with school hours
Hub North Scotland is the council's delivery partner for the Highland Investment Plan. Robertson Construction has been identified as the preferred main contractor.
Draft timeline
- June 2025 to October 2025: Statutory education consultation.
- December 2025: The Council agree plans to move St Clement's to a single site alongside a new Dingwall Primary School. News: Council agree £50 million investment in Dingwall Community Point of Delivery (PoD) - Highland Council
- 2027: Planning application to be submitted early 2027
- 2028: Work commences
- 2030: School Occupation
- 2031: Landscaping, demolition and all other works completed