Completed works schedule August/September 2024 S18
|
Works number |
Watercourse name |
Location |
Date works carried out |
Description of works |
|---|---|---|---|---|
|
641 |
Eil Burn |
Behind Burnside Lane |
12/09/2024 |
Remove vegetation along ditch. Priority increased following updated observation of increased weed growth. |
|
663 |
Beechwood Burn |
Opposite the Veterinary Centre on the B9006 Culloden Road |
06/08/2024 |
The outlet of structure 60 is suffering silt and vegetation deposition approx 90% surchaged, the inlet of structure 70 has similar issues although not surcharging, deposition is deflecting waterflows towards the sidewall, ditch burn 10 metres downstream from the outlet and 10m upstream from the inlet to return burn to original invert levels. |
|
730 |
Ardival Burn |
Rear entrance to Wyvis Hotel, Strathpeffer |
11/09/2024 |
Old Stone Culvert has collasped, causing Inlet to Pool/ Surcharge & overtop over Road. Culvert to be replaced with new Pipe & Headwall. |
|
732 |
Olrig Cemetery Burn |
Olrig Cemetery, road leading to St Trothan's Church, Castletown |
20/08/2024 |
Dual Stone Culvert/ Cundy has collapsed in middle of Culverted section parallel to Road. Multiple piles of side-cast Debris surrounding Screened Inlet U/S. Repair/ replace collapsed section, collect side-cast Debris near Screen. |