Road infrastructure

West Link project progress

Stage 1 – completed

  • Canal Parks enhancement completed in December 2017
  • new golf course and clubhouse completed in spring 2019

Stage 2 – underway

Construction began in June and is expected to be completed by December 2020. This stage includes:

  • a second swing bridge to prevent road traffic disruption from canal traffic
  • demolition of the existing golf clubhouse, with materials recycled (scheduled for late July/early August 2019)
  • realignment of General Booth Road, including utility works and resurfacing (scheduled for completion in 2019)
  • canal works including bridge foundations, wharf construction and service crossings (scheduled for November 2019 to March 2020)